What’s new in version 26.03
Approvers can now see who has sent a request from their Client Portal account. We’ve also deployed a few fixes behind the scenes as we prepare for upcoming features.
Questions about our new features? Get in touch with our Support team.
Client Portal
When a document is sent for approval, approvers who are using Aimsio to manage their requests can now see who has sent the request under the Submitted By column.
Job Performance (WBS)
We’ve updated the way Schedule Metrics are counted in a Work Breakdown Structure. Duration is now inclusive of both effective Start and End dates. In other words, if the effective start is Jan 1 and effective end is Jan 2, the Duration will be 2 days.